Week 6 - June 20-26, 2016



6/20 - day 36 - HVAC/plumbing
6/21 - day 36 - HVAC/plumbing
6/22 - day 38 - Pre-Drywall Meeting!
6/23 - day 39 - Electric
6/24 - day 40 - HVAC/plumbing/electric?
6/25 - day 41 - HVAC/plumbing/electric?
6/26 - day 42 - visit




Not much new or exciting to report that wasn't covered in the Pre-Drywall Meeting post from mid-week. We don't even have pictures.
It was all "guts" work all the time. Seemingly slow work on HVAC, plumbing, and electric.
We walked through Sunday evening and found almost everything completed.
Electric started after our pre-drywall meeting, so that was fun to see. It did appear that they had heeded my request (thanks other bloggers) to wire the garage carriage lights up to the front door with the switch for the front porch lights. Yay!
Did notice more spray paint notes likely from our PM to the framers on cleanup work we requested and other stuff he seems to have found on his own. Glad someone else is checking that important work!


Looking like this week will be framing fix-ups, insulation, spray-foam, inspections, etc.
Thursday night is looking the night the "elves" will sneak in to insulate the garage.


Can't wait to move on to drywall! This part is so not exciting!